Below you can see the maintenance jobs we have planned. If you see something that need fixing, please report this to the Maintenance Coordinator (see contacts page). They will review it and add it to the list, if appropriate. The maintenance team will work through these jobs as quickly as they can. Regular communication is via the maintenance team WhatsApp group.
If you would like to see improvements in the village, you will need to prepare a 1-pager proposal. This should list the benefits, approximate cost of implementation, ongoing maintenance, impact on village hall hire & events etc. The RFO will advise how you can do this. Once complete the proposal will need to be formally evaluated and approved before implementation.
If you would like to see improvements in the village, you will need to prepare a 1-pager proposal. This should list the benefits, approximate cost of implementation, ongoing maintenance, impact on village hall hire & events etc. The RFO will advise how you can do this. Once complete the proposal will need to be formally evaluated and approved before implementation.
Planned maintenace
Jobs we need to do every year:
January - March
- Annual PAT testing - completed Jan 26
- Annual Fire extinguisher testing - completed Jan 26
- Village annual walk around inspection - completed Apr 26
- Brief landscaping contractor - completed Mar 26
- Playground external annual inspection Feb 26
- Village litter pick & general tidy up
- Inspection of dykes
April - June
- Village Hall annual boiler service & gas safety check completed Apr 26
- Defibrillator maintenance service completed Apr 26
- Jet wash playground & benches - completed May 26
- Review asset register & renew Insurance completed July 26
July - September
- Tidy up raised bed at rear of hall - started & ongoing
October - December
- Inspection of dykes
- Replace smoke detectors (due 2030)
- Fuse box 5 yearly test (due 2030)
Reactive maintenace
Jobs reported, evaluated and due for fixing this year:
- Repair Bus Stop broken guttering completed 03/04/26
- Repair Bus Stop rotten side window completed 16/7/26
- Fit external tap completed 03/04/26
- Replace old & broken kitchen external waste pipes - completed 03/04/26
- Replace blown sealed units
- Fix rotten skirting at the rear of the hall - completed 14/06/26
- Fix poorly shutting Fire exit door - completed 04/06/26
- Fix emergency leaking indoor main tap - completed 26/06/26
- Fix disabled emergency pull cord - completed 09/10/26
- Fix slipped roof tiles on Hall - completed 02/07/26
- Replace front door lock - completed 03/07/26
- Repair childproof lock on under-sink kitchen cupboard completed 26/07/26
- Replace all out of date first aid kit - completed 30/07/26
- Remove wasps nest from village hall - completed 09/10/26
Improvements wish list
Improvement ideas suggested:
- Install projector & screen - completed 09/10/2026
- Install additional emergency lighting - completed 9/10/26
- Playground & football field grounds & trees tidy up Oct
- Repaint village hall main interior hall: 10 - 21 Feb 2027